A milestone inspection is required at 30 years after the certificate of occupancy, or at 25 years when the building is within three miles of the coastline, and every ten years after that. It applies to condominium and cooperative buildings of three stories or more.

The two dates

The clock starts at the certificate of occupancy, not the year the first unit sold. A building within three miles of the coast is inspected five years earlier than one inland — the law assumes salt air and wind-driven rain reach it harder.

How the counties differ

CountyProgramCycle
Miami-DadeCounty recertification, §8-11(f)30 years, or 25 within three miles of the coast, then every ten
BrowardBuilding Safety Inspection Program (BORA 05-05)25 years, then every ten
Palm BeachState milestone rule in unincorporated land; cities run their own 25 years coastal, 30 inland, then every ten
CollierState milestone rule25 years within three miles of saltwater, 30 outside, then every ten

What happens if the date passes

The building official can refer the case to the code board or the unsafe-structure process. A lender or insurer can require the report before renewing. That is why the deadline matters to an owner even before a notice arrives.

Where the deadline is published

Miami-Dade publishes every recertification case since 1996, and Broward publishes its yearly notification list. Palm Beach and Collier publish no bulk list, so a deadline there is calculated from the year built and the county's rule and labelled as calculated.