A building that fails a milestone inspection is not automatically closed. The report triggers a phase two inspection where the structure is questionable, then repairs that the building official tracks — with the association obliged to finish them.
The phase two inspection
Where the phase one report finds a structural problem or an area that cannot be judged without opening it up, the engineer performs a phase two inspection of that area and reports again.
The repairs
The association must complete the repairs the report requires, and the building official follows the case until they are done. Where the building is unsafe, the official can act sooner.
What owners should do first
Get the report, its scope and its repair list in writing, then price the repairs with licensed contractors. A lender or insurer will ask for the same documents.